APCO PLANT MILLER GYPSUM BUILDING
Project Type
New ConstructionLocation
Quinton, ALOwner
Southern CompanyGeneral Contractor
Brasfield & GorrieSubcontractor
Dunn Building CompanyDelivery Method
SubcontractSummary
For this project, Dunn furnished and erected a 34,920 SF pre-engineered gypsum storage building on the Alabama Power-Plant Miller Limestone Prep & Gypsum Dewatering Project. Project included galvanized primary and secondary framing, insulated standing seam metal roof system, 5:12 roof pitch. The building was designed and erected around and over the gypsum transfer conveyor and radial stacker (which was in place prior to building erection). Of significance, the building was 164' clear span structure with a ridge height of 60'2".